Hypothetical example: milestone cash schedule, $120,000 order in three deliveries
| Stage | Supplier paid | Cash out | Customer pays | Cash in |
|---|---|---|---|---|
| 1 (40%, ships week 2) | Week 1 | $30,300 | Week 6 | $48,000 |
| 2 (35%, ships week 6) | Week 5 | $26,700 | Week 10 | $42,000 |
| 3 (25%, ships week 10) | Week 9 | $19,000 | Week 14 | $30,000 |
| Totals | $76,000 | $120,000 | ||
| Cash out before first customer payment | Weeks 1 and 5 | $57,000 |
All figures are hypothetical. Cash out for each stage is the supplier price (60% of the invoice) plus freight of $1,500, $1,500 and $1,000. Customer invoices are Net 30 after each delivery. Your own terms will differ.
How do delivery milestones change the funding need?
Delivery milestones turn one large need into several smaller ones, so the right request is built from the peak cash out, not the grand total.
In the example, the customer order is $120,000 in three deliveries of $48,000, $42,000 and $30,000. The total you pay suppliers and carriers is $76,000. But by the time the first customer payment arrives in week 6, you have spent only $57,000, which is the $30,300 for stage one plus the $26,700 for stage two.
Write the milestones down with dates: ship date, delivery date, acceptance date if the customer inspects the goods, and invoice date. A funder reads that sequence as evidence you understand when money leaves and when it returns.
Should each stage get a separate invoice?
Yes, whenever the purchase order allows it. A separate invoice per delivery lets you start the collection clock at each stage instead of waiting for the final shipment.
The example uses Net 30 terms on each delivery, so stage one is collected about four weeks after it ships. If the order instead bills everything on the last delivery, the first payment would not arrive until week 14 and the whole $76,000 would be outstanding.
Read the purchase order before you plan. Look for language on partial shipments, acceptance, and whether the customer can hold payment until every stage is complete. If the terms are unclear, ask the customer to confirm in writing. Our guide on funding a large purchase order covers what a funder wants to see in the order itself.
How do supplier payment stages line up with the customer schedule?
Aim for the supplier to be paid in stages that mirror the deliveries, because paying one supplier in full on day one can force you to fund much more than the early deliveries require.
Ask the supplier whether they will release goods against a per-shipment payment. In the example, each payment falls the week before the goods ship: weeks 1, 5 and 9. If the supplier insists on the entire $72,000 of goods up front, add the $4,000 of freight and the peak cash out jumps to the full $76,000.
- Confirm in writing whether the supplier accepts stage payments.
- Ask whether prices hold across all three shipments.
- Check what happens if a shipment is delayed, and who bears storage or freight changes.
- Record each payment due date next to its delivery date on the schedule.
A flexible line of credit for buying opportunities is one structure funders review for repeat stage payments, because you draw as each stage comes due. Terms vary by product and by the strength of the business.
How do you avoid funding more than each stage needs?
Size the request to the peak cash out on your schedule, then compare it with the funding you would need if every payment were due at once.
Using the example, the difference is $76,000 against $57,000, or $19,000 of money you would carry without needing it. That is a real cost in a repayment schedule, and it is the first thing worth checking before you apply.
Build the schedule in a spreadsheet, add a row for the highest cash out before collections begin, and keep a small reserve for a late customer payment. Then attach the order, the supplier terms and recent business bank statements to a single request.
A decision typically comes within 24 hours of a complete application, and funding time varies by product. Describe the stages and your deadline in the one online application. For a single signed order, the funding to fulfill a purchase order page explains how it is reviewed.
If the margin on a stage is too thin to cover the funding cost, say so in your own plan and consider renegotiating the order rather than accepting it as written.
Frequently asked questions
Can I fund only the first stage of a purchase order?
You can describe the whole order and ask for what the early stages need. The funder reviews the file and decides what to offer. Attaching the full schedule shows the later collections that support repayment.
What if the customer pays only after the final delivery?
Then all stage costs stay outstanding until the end, and the request grows to match. Ask whether the customer will agree to pay per delivery, and put the answer in writing before you apply.
Do I need a separate application for each stage?
No. Describe the full order and its stages in one application. The funder reviews the whole file, including the delivery schedule, the invoices and the supplier terms.
How do I show the supplier payment stages?
Attach the supplier quote or agreement that lists each payment and its due date. If terms are verbal, ask the supplier to confirm them in an email so the file has something to show.
Is there an obligation to accept an offer?
No. You can review an offer, compare the written numbers and decline. Checking your options does not affect your personal credit score.
Describe your purchase and deadline
Share the stages, invoice terms and supplier terms in one application.
Updated October 17, 2026 · Prime Funding Now Funding Team